Another long awaited update to the blog (hopefully!) Over
the past few weeks we have been tricking on with a few of the more mundane
tasks that our gang has to deal with, such as the monthly line walks, checking
spot reports of roughing riding etc, the continued packing of the south point
at Parkend. This particular bug bear has been going on for weeks as the ballast
has a tendency to settle into the underlying ash ballast that the original
Severn and Wye track bed was built on. This combined with the leakage of the
water tank in the embankment above the track has resulted a bed that has been
soggy for many years. This leak has been fixed by the sterling efforts of our
Civil Engineering team. It is hoped that now the trackbed will have a chance to
dry out, aiding our ability to consolidate the ballast to an acceptable
standard. This will please our friends in S&T no end!
Building bridges between the various gangs is a always a
practical thing to do and in the last week or so we have assisted the S&T
gang working at Parkend by helping them move a shedload of the necessary
concrete mounting and troughs for their work in commissioning the new signalbox
there.
Works train headed to Parkend.
Shifting concrete outside the 'box.
Plus it is always fun to get a ride in the brakevan and 08
shunter on a working day!
In our last update we mentioned our problems with our
Dogfish fleet, more specifically to do with the over ambition of the brakes to
do their job. Due to my days off not coinciding with the working days for our
gang, I took it upon myself to see what could be done about this.
After investigating and stripping the majority of the
linkages out, it was discovered the main problem was due to the bell crank that
attaches the vacuum cylinder to the brake linkages. Essentially the brake had
pulled hard on, but the corrosion in the system prevented the weight of the
linkages pulling them off again.
This crank was seized solid.
This crank should in fact hang free and move under its own
weight. Unfortunately due to many years of standing with little or no use, the bearing
faces inside had rusted and gripped the ends of the shaft with a tight
grip.(Ten minutes with a lump hammer to shift it 3 inches.....) One short trip
to Travis Perkins over the road and shares in 3-in-1 oil and WD40 had
skyrocketed.
The 4 bolts holding the brackets were removed slowly and the
whole assembly was lowered out delicately. For delicately read ‘wellied with a
sledge and timber drift until it came loose.’ All that remained was to chip off
the rust lamination on the faces of the brackets which was helping to tighten
everything up, scrape the powdered rust out of the bearing faces, add judicious
amounts of grease and reassemble.
Its free. Note the thick rust dust on the ends of the axle.
All that remains now is to have it tested under vacuum,
something we hope will happen ASAP so we can fill it in preparation for a
ballast drop.
Speaking of ballast we have been lucky enough to have
Quattro training on our railway in the last week with some very interesting
bits of kit. They have been trailing a road/rail lorry based ballast vac. This
bit of kit can shift more ballast in an hour than a full gang can shift in a
days work apparently. I can well believe it!
This is one epic bit of kit!
This is far easier than pulling back with shovels!
The RRV is pretty handy too.
The other bit of kit was the RRV 360 with its
associated flat wagon. They were using this to place bags of ballast around the
working areas for the blast vac to use and train with as well as doing a spot
of lineside flailing, a never ending task for our lineside gangs so they were
pleased to have mechanised help. They are another impressive piece of kit and
very useful. Possibly even more importantly however, they will kindly be
donating the ballast they are training with once they are finished. Every
little helps!
Something to look forward to in the coming week or so is the
return of two 360 RRVs. Although they are training themselves, we
will be on hand to get them to move, lift and otherwise relocate kit we have
been meaning to get moved in ages. These should provide an interesting week of
work and the associated pictures for you followers out there.
There are also rumours of a mainline tamper visiting us in
the near future, making use of our mainline connection. Watch this space!
For those readers outside of the bounds of the Forest of
Dean, our long term plans for the DFR were published in the local paper The Forester.
.
It makes an
interesting read and I feel cements the future of the railway in the local
area. Exciting times are ahead of us,
and if you feel that you would like to get involved in any way, please don’t
hesitate to get in contact with us. Either at Norchard, through this blog, or
this weekend (26th and 27th September) at the Lydney
Model Show.